Analysing the Scope of Force Majeure in the Light of Covid-19.

View PDF Full text XML Google Scholar
25views1downloads
Published 9 September 2020 · pp. 1695–1712 · Vol. 3, Issue 4 (2020)
Abstract

The outbreak of the COVID-19 disease has been declared a global pandemic by the World Health Organization (WHO) on March 1, 2020. The outbreak has not only affected humans but has also resulted in a global economic shock. The need to maintain social distancing and lockdown has resulted in slow operations of many businesses and has ultimately affected the diverse commercial contracts. In such circumstances a force majeure clause is considered to be a strong defense against such unavoidable and unforeseeable events and helps parties discharge their contractual obligations wholly or partly without making them liable for non-performance of their contractual obligations. Through this article, the authors would try to analyse the scope of force majeure clause in diverse contracts, in the light of the ongoing coronavirus pandemic and related governmental measures to curb it. In the similar context, the authors would further elucidate the various criteria that companies must fulfil in order to successfully invoke the force majeure clause in their contracts in the present situation of Covid-19 pandemic. The article further tries to enquire about the possible steps to be taken if a force majeure clause is absent in a contract and is also suggestive about the course that should be followed before invoking a force majeure clause. The hypothesis of the article defines how COVID-19 triggers the force majeure clause. The authors have also tried shedding light on how is India dealing with force majeure clause in diverse contracts including real estate contracts, supply chain contracts, employment contracts, Insurance contracts etc

Keywords
COVID-19PandemicContractual obligationsWorldwideEconomic impactSocial distancingLockdownCommercial contractForce majeure clauseIndia
Contents
Full text

Introduction

On March 11, 2020, the World Health Organization (WHO) declared Covid-19 virus a global pandemic. Novel Coronavirus or Covid-19 disease has been identified and classified as SARS-CoV2 (closely related to SARS-CoV) which is another form of zoonotic coronavirus. These zoonotic coronaviruses can cause health ailments ranging from cold and cough, fever to acute respiratory syndromes like the Severe Acute Respiratory Syndrome (SARS) in 2003 and the Middle East Respiratory Syndrome (MERS) since 2012. 3 The newly discovered coronavirus has swamped 215 countries, areas and territories, affected over 39,00,000 people and has claimed 2,77,000 lives.4 The accelerated spread of COVID-19 has brought the world economy to a standstill and the International Monetary Fund (IMF) in its global growth projections during mid-April has stressed that the global economy is expected to experience its worst recession since the Great Depression.5 Even the Indian economy is supposed to expand at 8% which is the lowest in the last eight years.6 The world trade is also expected to fall between 13% and 32% due to the present disrupted global economy and exceed the trade slump brought on by the global financial crisis of 2008-2009.7

The coronavirus outbreak has affected almost every sector of business and industry including financial sector, tourism, real estate and manufacturing etc. and companies have now started disclosing their liquidity measures to face the economic impact of the outbreak of corona virus. The airplane industry is suffering from restriction to travel to affected locations and thus various international airline holdings like the United Airline Holdings from U.S has announced reduced flight schedules. Other industries like the Purell manufacturing company Pfizer have also reduced production.8 Chinese factories have reported their lowest Jan-Feb profit in ten decades, this year. Companies with major operations in places like China and Italy have also decided to reduce their operation. Many commercial giants such as Apple and Haidilao have closed outlets in China until further notice.

In the last two months the world has been a witness to series of unprecedented and unforeseen circumstances in the form of reduction in trade and output, disruption of supply chains and business operations, reduced employment etc. caused due to the outbreak of Covid-19 disease. It is evident that these unforeseen effects of Covid-19 have resulted in the non-performance of innumerable number of diverse contracts and the parties failing to comply with the contractual obligations are likely to take the recourse of force majeure clause present in the contract or agreement to get released from contractual obligations. The term force majeure finds its origin in the French Civil law and has no doctrine under the common law. Although there has been no statutory definition of force majeure till date but the convention relating to a uniform law on the international sale of goods which took place at Hague in 1964 has given a standard definition of force majeure. According to article 74, Uniform Law on the International Sale of Goods (ULIS), where one of the parties has not performed one of his obligations, he shall not be liable for such non-performance if he can prove that it was due to circumstances which, according to the intention of the parties at the time of the conclusion of the contract, he was not bound to take into account or to avoid or to overcome.9 These circumstances have been referred to as force majeure.

How Can Parties Invoke Force Majeure Clause in the Light of COVID-19?

There are circumstances which are beyond the control of a reasonable man and in such circumstances a force majeure clause can be sufficient to prove that such an act leads to the impossibility of performance of the contract. Although there are no specific standards to prove a force majeure event and mainly depends on the drafting of the force majeure clause under the different contracts and its interpretation by the court, there are certain standard formats which are used worldwide for determining force majeure clause. One of them is the UNIDROIT Principles of International Commercial Contracts (UPICC)10 which lays down certain elements which should be satisfied to invoke the force majeure clause. First, the impediment was beyond the control of the party and no reasonable prevention could have been taken with respect to the impediment. Second, the excuse of temporary impediment for invoking the force majeure clause can be taken for as long as the impediment is affecting the performance of the contract. Third, when there is failure of performance of contract by one party, a notice must be sent to the other party within a reasonable time about the impediment and its inability to perform due to the same. Fourth, invoking force majeure clause does not prevents the party from its right to terminate or withholding the performance of the contract.

Before invoking force majeure clause, the parties need to consider some points which are as follows-

1)  RELEVANT PROVISIONS IN THE CONTRACT- The parties need to determine if the particular contract includes the clause of force majeure and if there are any other provisions which can be assessed.

2)  LAW GOVERNING THE CONTRACT- The party needs to determine which law is governing the whole contract and how will the force majeure clause be interpreted under the applied law.

3)  SCOPE OF FORCE MAJEURE CLAUSE IN THE CONTRACT- The party needs to assess if the contract explicitly contains the list of the events which qualify as force majeure or has generally defined the term force majeure which can be interpreted openly.

4)  DELAYED OR NON-PERFORMANCE CAUSED DUE TO THE EVENT- The party also needs to prove the level of interference experienced by them due to the event before invoking the force majeure clause.

For the parties to invoke force majeure in the light of COVID-19 the main issue that parties need to assess is whether the contract has explicitly mentioned about the event or the outbreak of the event can be implied even if it is not referred in the force majeure clause? It is often seen that in a contract a force majeure clause is narrowly construed and contains the list of specific events and those events which are specifically excluded from the list cannot be availed by the parties.11 Since the outbreak of Coronavirus is being dealt first time by the world and the consequences of this outbreak is unforeseeable, it can be assumed that no contracts would have included COVID-19 as one of the events listed under force majeure clause nor it can be specifically excluded from the force majeure clause. However, parties can contend for implied exclusion to be granted if the parties fail to prove that COVID-19 satisfies all the elements of force majeure clauses. In India, the Delhi High Court in the case of GV Projects & Investments (P) Ltd. v. National Highway Authority of India (2019) 173 DRJ 717, stated that force majeure would arise if the impediments are caused due to unforeseen events which are relatable to the express and implied clauses in a contract.12 Thus, defaulting parties can try to impliedly cover the various government actions taken during Covid-19 disease like lockdowns, ban on transportation, quarantine measures etc. under the ambit of various force majeure clauses like governmental regulations, bans, strikes etc.

DOES COVID-19 SATISFIES ALL THE ELEMENTS OF A FORCE MAJEURE CLAUSE?

After covering the unforeseen event impliedly or expressly under the force majeure events present in the contracts, parties need to fulfill the elements in order to successfully invoke non-performance. The elements of force majeure vary from contract to contract as they solely depend on the language used by parties during closure of the contract. However, the authors for the purpose of the article have taken references from international bodies in order to establish standard elements to be fulfilled in order to successfully invoke a force majeure clause. The China Council for the Promotion of International Trade (CCPIT) laid down two components as a proof for delayed or non-performance of the contract and based on these components it issued its first force majeure clause certificate to an auto parts manufacturer in Huzhou, Zhejiang Province in the light of COVID-1913. Therefore, the following two components can be considered necessary elements to be proved in order to successfully invoke a force majeure clause:

1)  Unforeseeable occurrence- Whether the consequences of the outbreak was foreseeable and whether it could have been mitigated by taking reasonable measures?

China’s strict social distancing and announcing full as well as partial lockdowns due to the spread of COVID-19 have been considered to be an unforeseeable event. There have been many unprecedented events all around the world including India such as disruption of market, supply chains, financial crisis has created a great impact on the global economy leading to non-performance of the contracts by the corporations14. The restriction of movement of migrant workers will affect the manufacturing sector which will ultimately affect the supply chains of many big corporations. The unforeseeable outbreak of Coronavirus has also created a great impact on off-road vehicles market due to the inability of accessing the sites of the projects in most affected places such as China, Germany, U.S and delayed supply chains.15

However even if the outbreak is considered to be an unforeseeable event, there are chances that the contract can be enforced by mitigating the effects of the outbreak of the event on the contract. It was held in the case of a flu (SARS, 2003) that "…if a contracting party can otherwise continue to satisfy its contractual obligations in a commercially reasonable manner, the force majeure clause will not operate to absolve that party from its contractual responsibilities."16 The outbreak of coronavirus and its consequences have been considered to be more severe than any other epidemics and therefore a party failing to perform the contract can prove that the spread of COVID-19 is unprecedented and the consequences of such an outbreak is so intense that it could not have been foreseeable for a party to take reasonable steps to prevent the event.

2)  Whether the outbreak of the event has impacted the performance of the contract?

To establish a link between the non-performance of the contract and the outbreak of the event the party need to prove that the event was the sole cause of the non-performance.17 Another question which has to be answered by the party is that breach or non-performance would have not occurred if there were no lockdowns and advisories related to the outbreak of the event. The Singapore court has also ruled out that the difficulties arising due to government orders related to supply chains or bans can be considered under force majeure clause18. Similarly, in the case of Halliburton Offshore Services Inc. v. Vedanta Limited and Another19 the respondent had granted an extension for the completion of the project but the plaintiff was not able to perform the contract owing to complete lockdown due to COVID-19 pandemic and therefore invoked force majeure clause. The Delhi High Court held that the lockdown due to the outbreak of the pandemic as well the non-performance of the contract due to the ban on overseas travel during the outbreak is considered under force majeure clause. However, in the case of Standard Retail Pvt. Ltd. v. M/s G.S. Global Corp & Ors20. the Bombay High Court refused the injunction stating that the contract contained the steel distribution and according to the government lockdown guidelines the steel distribution was considered as an essential service therefore there was no restriction on the steel transportation and therefore the consequences of the outbreak of COVID-19 pandemic did not affected the performance of the contract.

The onus of proving whether COVID-19 falls within the ambit of force majeure clause lies on the party who needs to discharge itself from the obligations to perform the contract and needs to take both the points into consideration.

How Is the Scope of Force Majeure in Diverse Contracts Being Dealt with in India?

The series of nation-wide lockdowns imposed by the government in order to curb the rapidly spreading coronavirus has had an impact on almost every sector of business in India. The lockdowns have resulted in the country’s economic standstill, shrinking factory outputs to a record 7.1% in March.21 The central and state governments have been granted powers under section 2 & 2A of the Epidemic Diseases Act22 in order to take necessary steps (lockdowns) in order to control the outbreak of epidemic. Also, the Ministry of Home Affairs, Government of India, vide the powers conferred upon them by the National Disaster Management Authority (NDMA) under Section 10(2)(1) have issued guidelines under Order No. 40-3/2020-DM-I-(A), for closure of all commercial and private establishments except for essential commodities.23 This has immensely resulted in disruption of various supply chains, thrown businesses and manufacturing industries in a state of disarray, increase in unemployment, automobile & real estate sectors have come to a grinding halt and has prevented the performance of obligations by parties in diverse contracts. In the light of the prevalent situation, the authors would like to analyse the force majeure clause in the below mentioned types of contracts:

1. Real Estate Contracts (Contracts formed under the RERA Act, 2016 & Lease Agreements): Contracts pertaining to the real estate transfer include the use of immovable property in the form of lease and agreements under the Transfer of Property Act, 1882 and contracts formed under the Real Estate Regulation Authority Act, 2016.

Contracts formed under the Real Estate Regulation Authority Act, 2016 and the Indian Contract Act, 1872 have to be assessed under the two following heads in the present situation:

a. Validity of registration under the RERA Act, 2016: Section 4(2)(C) of the Real Estate Regulation Authority Act, 2016 states that an application of registration submitted to the regulatory authority must contain the time period undertaken by the promoter to complete the project.24 Section 5(1)(3) of the same act provides that the registration would be declared for a time period as mentioned by the promoter according to section 4.25 It is fair to consider that the parties entering into contracts before the month of March could not anticipate the onset of the Covid-19 disease and the related regulatory (lockdown) measures. Thus, delay caused due to the lockdowns and supply chain disruptions has extended the time period required to complete the project and will lead to termination of registration before completion of the same. Relief for such unforeseen and unprecedented force majeure events has been granted under section 6 of the RERA Act on account of an application made by the promoter. Force Majeure events in the RERA act, consists of war, flood, drought etc. and other natural calamities caused by nature.26 Thus, promoters can contend to the regulatory authority for extension of registration on the ground that the sudden outbreak of Covid-19 equates to an unforeseen calamity.

The central and state governments too are striving their best in order to destress the promoters and developers from strict RERA timelines and to protect the interests of the home buyers in the present situation of pandemic. The Ministry of Housing and Urban Affairs (MoHUA) through an official communication on May 13, 2020, stated that the ministry will send an advisory to the states and union territories to treat Covid-19 as a force majeure event. The ministry has further assisted the states, union territories and their regulatory authorities to Suo Moto increase the completion and registration time period by six months, for projects registered after March 25, 2020. The government of Maharashtra too, in its order no.: - 13/2020 dated April 2, 2020 stated that all registered project under MahaRERA, whose completion date is after March 15, 2020 must get registration/completion time extended by 3 months27 and MahaRERA would also be providing certificates for the same. Karnataka RERA Authority vide its circular dated April 6, 2020, has similarly extended the registration of all real estate projects by a period of three months, in cases where registration is expiring after March 15, 2020. These orders considering the outbreak of Covid-19 has abated the need for promoters to prove that Covid-19 can be considered as a force majeure event under the required national and state legislatures thereby releasing them from non-performance.

b. Delivery commitments to allottees: The sudden outbreak of the Novel Coronavirus has also affected the individual contracts of promoters with allottees pertaining to the delivery of immovable property. In this context, promoters need to check their agreement and comply properly with the present contractual provisions pertaining to force majeure in order to escape contractual obligations or non-performance. The promoter must take necessary steps including sending notice to the allottees and showing the effect of the event on performance.

A special emphasis must also be paid to the force majeure clause in various ‘model form of agreement’ between promoter and allottee provided by various states. The clauses in these agreements can be modified and used but cannot be made contrary. Promoters must check how can they bring Covid-19 under the ambit of the force majeure events mentioned in the agreement of various states. For e.g. ‘in the model form of agreement’ as per rule 10(1) of The Maharashtra Real Estate (Regulation and Development) (Registration of real estate projects, Registration of real estate agents, rates of interest and disclosures on website) Rules, 2017, promoters are to be granted extra time to deliver the property to the allottees if their work is hampered by any force majeure event including war, act of God, notice from the government or competent authorities.28 Similarly, the Force Majeure clause in the Model Agreement to Sale as prescribed under Rule 9 (1) of the Gujarat Real Estate (Regulation and Development) (General) Rules, 2017 also states that extra time will be provided to the promoter for delivery if the delay is caused due to force majeure events including war, act of God or notices by government or competent authorities.29 Thus, these orders have made it easier for the promoters to invoke force majeure clause and get an extension for the fulfilment of their contractual obligations. The regulatory orders passed by the governments including the orders for the extension of registration time period and the government guidelines regulating movements by the Ministry of Home Affairs (MHA) etc. validates as notices from government and competent authorities and will help the promoters invoke force majeure and get an extension for delivery of property to allottees.

Contracts in the real estate sector related to lease of immovable properties are covered under the Transfer of Property Act, 1882. In the present light of Covid-19, parties who have already entered into a lease agreement, particularly the lessor may face certain drawbacks. In order to invoke non-performance due to a force majeure event, the lessor must pay emphasis to the provisions of the lease deed for a force majeure clause, impliedly or expressly covering Covid-19 and related governmental measures. In the absence of a force majeure clause the lessor cannot contend impossibility of performance under doctrine of frustration, Section 56 of the Indian Contract Act, 1872 as lease deeds do not apply to contract law.30 The lessor can check if the present situation falls under the provisions under Section 108 of the Transfer of Property Act, 1882. This section states that the lessee can consider the contract to be void if any part of the property is destroyed or rendered substantially and permanently unfit for the purposes for which it was let, by fire, tempest or flood, or violence of an army or of a mob, or other irresistible force.31 It is evident that the clause doesn’t cover the hinderances created by the present situation of Covid-19. Thus, the lessor needs to study the intricate language of the force majeure clauses mentioned in the agreement in the light of the current circumstances. In the current situation of crisis in order to prevent unnecessary litigations, the parties are at liberty and have the last resort to renegotiate the agreement to include a necessary force majeure clause in order to extend the performance period and resolve the situation amicably.32

2. Supply Chain Contracts (Financial Transactions): Covid-19 and related governmental measures has had an adverse effect on the supply chains and resulted in delay, interruption and disruption. Present lockdowns have created in ripples in the supply chains across the world and has resulted in failure in performance and delay in production, ultimately drawing the attention of parties to the force majeure clause present in their contracts.

The present coronavirus outbreak has also impacted and disrupted the foreign supply chains resulting in non-performance of the present government supply contracts in India. The government has taken due cognizance of the same and in this regard vide an Office Memorandum (O.M.) No.F.18/4/2020-PPD, dated February 19, 2020, through the Government of India, Ministry of Finance, Expenditure Department, has stated that the disruption of supply chain due to the present outbreak of Covid-19 in China or any other country will be treated as natural calamity and will be covered under force majeure clause/events in the government’s manual for procurement of goods.33 The ministry of Finance, government of India created the manual for procurement of goods in order to increase transparency and proper execution of government/public procurement. Clause 9.7.7 of the manual defines the ambit of force majeure clause in public procurement which includes events natural calamity (act of God), war, riot etc. and other unprecedented events. The clause inter alia states that if contracts formed under the manual get delayed for more than 90 days due to the above-mentioned events, it can be terminated at the option of either party.34 Thus, now if the government fails to comply with its contractual obligation of suppling goods, due to the disruption of relevant supply chain of goods being procured by them, the government can invoke force majeure for extension of period of performance or termination as the O.M. considers the present outbreak as a natural calamity under the force majeure clause. However, the following procedural changes would not grant any relief to private procurement and supply companies as the O.M. only affects procurement by government ministries and departments as well as entities that are substantially owned or controlled by, or receive substantial financial assistance from the Central Government.35 Thus, for private suppliers who are involved in procurement have to examine their contract closely and check whether the ambit of their force majeure clause includes the present outbreak in order to excuse their contractual obligations. If a force majeure clause is missing in the contract, the parties can always contend impossibility of performance under Section 56 of the Indian Contract, 1872 as an agreement to do an impossible act is void in itself.36

solar Independent Power Project contracts (including Power Purchase Agreements) in India. The non-performance of IPP contracts or failure on the part of project developers to complete the project within commissioning date results in liquidated damages to be paid to implementing agencies. Currently, most of the PPAs consist of a force majeure clause stating events both natural and non-natural like act of god war etc. In the light of the present outbreak of Novel Coronavirus, the issue whether COVID-19 would qualify to be a FM event under the solar PPAs has been put to rest by the Ministry of New and Renewable Energy.37 In order to grant relief to the solar industry, the Government of India, Ministry of New and Renewable Energy (MNRE), in line with the Ministry of Finance's Office Memorandum of February 19, 2020, has decided to grant time Extension in Scheduled Commissioning Date of RE Projects considering disruption of the supply chains due to spread of coronavirus in China or any other country as Force Majeure (FM) event, via an Office Memorandum (No. 283/18/2020-GRID SOLAR) on 23.03.2020.38 In this regard, all the Renewable Energy implementing agencies under the Ministry of New and Renewable Energy (MNRE) for e.g. SECI, NTPC etc. have been asked to grant extension of time (EOT) for the completion of projects due to disruption of supply chains, caused due to the outbreak of coronavirus in China and any other country. Inter alia the O.M. also states that the project developers must provide proper evidence to connect their non-performance and disruption of supply chain due to coronavirus. Implementing agencies have also been asked to ensure that no double relief is granted due to overlapping periods of time extension granted for reasons eligible for such relief. Currently, most of the PPAs consist of a force majeure clause stating events both natural and non-natural like act of god war etc.

3. Employment contracts (Excluding work from home): The outbreak of the Novel Coronavirus and related lockdown measures to curb it has immensely affected almost every sector of business and industries in India. Key sectors of Indian manufacturing industries have shut down following lockdown orders from central and state governments. For e.g. largest cement production industries have decided to stop their production in factories across the country including states like Tamil Nadu, Andhra Pradesh, Rajasthan etc.39 leading to the estimated GVA to fall sharply by 5% in the FY21. This current situation of shutting down of factories and seizure of operations have led to an extensive reduction in employment all over the country. Centre for Monitoring Indian Economy (CMIE) said that unemployment rose to 27.11% in the mid-march.40

An employer is under contractual obligations to provide work and required remuneration to their employees. But currently, due to lack of revenue generation, employers have started revisiting the employment contracts formed with their employees in order to check whether a force majeure clause present would help them lay-off or retrench their employees or cut-off their wages temporarily. Usually, there are no force majeure clauses present in an employment contract or appointment letter but depending on the nature of employment force majeure clauses pertaining to termination and salary cuts may be present. For e.g. in fixed period employment in international and private organizations have specific clauses pertaining to the termination of employee after completion of tenure. In such cases, where contracts contain a force majeure clause the employer must pay detailed attention to the language written in the clause. However, in this context employers must be aware that labour laws supersede the labour/employment contracts i.e. termination or reduction of wages through a force majeure clause cannot be violative of the respective statute. In the absence of a force majeure clause or an employment contract, the employer needs to rely on relevant statutes in order to change terms of employment. In India, the terms of employment of the workmen (blue collar) are covered under the Industrial Disputes Act, 1947. Section 25M of the act states that only be laid off during shortage of power due to unprecedented events like a natural calamity and Section 25C of the act, inter alia states that when a worker working under an employee for more than one year is laid off, the employer needs to pay him for all such days he is laid off. Section 25G of this act states conditions precedent to the retrenchment of a worker. A worker who has worked under an employee for more than one month cannot be retrenched without a notice and wages a month prior to the retrenchment.41 The act also covers provisions for change in wages as change in terms of service. Section 9A of Industrial Disputes Act states that changes in conditions of service can be done by giving prior notice to the workers to be affected by such change.42 Terms of employment of non-workmen (white collar) employees are covered under the Shop & Establishment Act of the respective state they work in. For e.g. Section 30 of The Delhi Shops Act, 1954 states that an employer cannot terminate an employee who has worked in the corporation for more than three months without giving him a notice and wages prior to 30 days of his termination.43 Similarly, Section 39 of the Karnataka Shops and Establishments Act, 1961 states that an employer cannot terminate an employee who has been in service for the last six months, without giving him a notice and required wages prior to one month of termination.44 Employers must also take into consideration that any change or reduction in wages by an express consent cannot override the Minimum Wages Act, 1948.

Thus, from the above-mentioned provisions it can be considered that even in the absence of a force majeure clause changes can be made in the terms of service but the present government directions have put the use of force majeure clauses in employment contract to question. The guidelines passed by the government has provided relief to the workers/employees but have resulted in a massive backdrop for the employers. For instance, the Ministry of Labour and Employment via D.O. No. M-11011/08/2020-Media, has advised all private/public establishments not to terminate their employees and has stated that workers taking leaves would be considered to be on duty and their wages cannot be deducted. The D.O. has further stated that employees/workers whose employment has been made impossible due to the current outbreak or who cannot work from home, should be considered to be on duty.45 The Ministry of Labour and Employment, further on 30.03.2020 issued an advisory, D.O. No: CLC (C) / Covid-19/ Instructions / LS- I, stating that employers cannot terminate their employees including casual and contract workers and also cannot reduce or deduct their wages for the period during which the employees avail quarantine leave.46 The Government of India, Ministry of Skill Development and Entrepreneurship, via O.M. No. MSDE- 1(3)/2020AP(PMU) on 30.03.2020 has stated that it is mandatory for all establishments to pay full stipend to their apprentices engaged in their respective establishments under both designated and optional trade during lock down. Further, the O.M. stated that the government will reimburse stipend to establishments under National Apprenticeship Promotion Scheme (NAPS) as per the NAPS guidelines. Thus, it is evident to say that in the current situation, employers are at a disadvantageous position in order to invoke a force majeure clause in their contract or contend impossibility to provide working conditions and salary/wages as the recent advisories/notifications by the government authorities have reduced the scope and application of force majeure in employment contracts.

4. Insurance Contracts (Life Insurance): The outbreak of the Novel Coronavirus has almost engulfed the entirety of the country claiming more than three thousand lives. The present death toll due to the Novel Coronavirus has made a steep rise in the claims for death benefit or coverage amount from the insurance companies. It is fair to say that like most other business sectors, the insurance companies too have been facing unprecedented challenges in the face of the outbreak. Strain on investment portfolios due to turmoiled market conditions have made it difficult for the insurance companies to generate returns in the present situation of rising death tolls. Generally life insurance contracts in India, contain a force majeure clause which states that in the case of unprecedented events like natural calamities, strikes, pandemics etc. which disrupts the normal functioning of the company, claims for serving the policy, including policy related payments are temporarily suspended. This gives the insurer the power to temporarily suspend claims or death benefits in light of such unforeseen situations like pandemics.47

A recent declaration by the Life Insurance Council (the face of the Indian life insurance industry) in a press release on April 2, 2020 has rendered futile the usage of force majeure clauses in life insurance contracts, where death is pertaining to Covid-19. The council stated and confirmed that insurance companies cannot invoke the force majeure clause present in their insurance contract for any death claim pertaining to Covid-19 and both public/private insurers have to attend the Covid-19 related death claims at the earliest.48 Thus, insurers/insurance companies need to cover deaths due to Covid-19 as deaths due to illness, as would be considered in normal circumstances. Following the official declaration, Life Insurance Corporation (LIC) of India has settled 16 death claims across the country due to Covid-19 so far.49 Further, the Insurance Regulatory and Development Authority of India (IRDAI), in the light of the global pandemic, via an official press release, Ref: IRDAI/Life/Grace Period, on May 9,2020, has decided to grant an additional grace period of 30 days till May 31,2020, for the policies where premium fell due in the months of March 2020 and April 2020, keeping in view the difficulty faced by some policyholders to renew the policies in time.50

Thus, it is evident that the recent governmental guidelines have posed certain drawbacks on the insurance companies. Inability to invoke force majeure clause in life insurance contracts where death is pertaining to Covid-19 and regulators urging insures/insurance companies to accept delayed payments have made it difficult for the insurance companies to work efficiently in the light of the present pandemic. Considering Covid-19’s massive impact on human lives, it can be fairly anticipated that Covid-19 will fairly determine the policy premium and returns in life insurance contracts in the near future.

Suggestive Measures/ Alternative of Force Majeure Clause

Where there is no basis for the parties to invoke force majeure clause because of the absence of either written contracts or explicit mention of the issue of force majeure in the contract, the common laws provides various established theories for excusing the party for the non-performance or termination of the contract. The theories which can be used as an alternative of Force majeure clause are-

1) IMPOSSIBILTY OF CONTRACT

The doctrine of impossibility is recognized by the common law as a defense for the impossibility of the performance of the contract or other contractual breaches. The doctrine of Impossibility is interpreted narrowly and is restricted to the destruction of the means of performance by an Act of God. Black’s Law Dictionary has defined Act of God as “an overwhelming, unpreventable event caused exclusively by forces of nature, such as earthquake, flood or tornado. Similarly, The Restatement (Second) of Contracts has recognized the defense of “Act of God” under the definition of section 26151 which states that if a party needs to prevail the defense of commercial impracticability it needs to shows that an event was either an act of god or the act of third party making the performance impossible due to the unforeseeable event or due to the default of one of the party. Therefore, if the terms of the contract do not list “pandemic”, “epidemic”, “quarantine” under force majeure clause, parties can take the excuse of the more general terms used in the force majeure clause such as “disaster”, “Act of God”, “emergency”. For instance, in the case of Lakeman v. Pollard52 , The Maine Supreme Court held that the outbreak of cholera comes under “Act of God” and the court discharged the duty of the petitioner under the contract stating that the plaintiff was under no obligation to risk his life by performing his task during cholera outbreak which could not be controlled by a reasonable and prudent man. Applying the doctrine of impossibility to the COVID-19 outbreak, the party needs to clear its position whether the non-performance of the contract occurred due to the outbreak of the pandemic or due to the human intervention to claim the defense of “Act of God” if mentioned in the force majeure clause of the contract. However, The Supreme Court of India in the case of KSRTC v. Mahadeva Shetty53 held that every unexpected natural event cannot be considered under “Act of God” therefore Indian courts have not yet ruled out if a pandemic/epidemic falls under the ambit of “Act of God”. Even if there is absence of “Act of God” in the force majeure clause of the contract various other terms such as “act of government” under the force majeure clause can discharge the party from non-performance of the contract. In the light of COVID-19 government across the world declared lockdowns, emergencies, restriction on movement etc. which can be considered a strong defense for the party specially the traders and companies to invoke force majeure clause which includes such government acts.

2) FRUSTRATION OF CONTRACT

The Doctrine of Frustration got its root from the English Law which helps in disabling the obligations of the party to perform the contract due to the occurrence of unexpected and unprecedented events. The doctrine of frustration terminates the contract automatically without the action of the parties. A party can take the defense under this doctrine if the party is able to prove that the outbreak of the event was an unforeseeable event and no party was at fault. It also needs to prove that the event altered the performance of the contract. However, it is not very well ruled out whether a pandemic can be a reason for the party to frustrate the contract. A decision was given on a case by the Hong Kong District Court in which it was ruled out that Severe Acute Respiratory Syndrome (SARS) did not frustrated the contract between a tenant and the landlord54. Therefore, the party to excuse itself from the impossibility of the performance of the contract to the outbreak of COVID-19 there has to be a proper analysis of the contract and also need to assess the effect of the outbreak of the pandemic on the performance of the contract.

However, under Indian Law the doctrine of frustration is defined under Section 56 of Indian Contract Act, 187255.The doctrine rules out a positive rule of law for the impossibility of the performance of the contract by interpreting it practically.56 Therefore when there is absence of force majeure clause in the contract or if the force majeure clause contains restrictive events, the party can argue that Section 56 of the Indian Contract Act can be invoked to discharge the party from the performance of the contract since the epidemic is not mentioned in the force majeure clause. Therefore, for taking the defense of Doctrine of Frustration in the light of COVID-19, the party needs to prove that the incapability of performing the contract was due to the outbreak of COVID-19 and not due to the fault of other parties.

Conclusion

Novel Coronavirus (SARS-CoV-2) is an additional form of zoonotic coronavirus that has recently emerged as an outbreak, affecting people with a number of health ailments and causing innumerable deaths around the world. The outbreak of the Covid-19 disease is deadly and the worldly lockdown measures in order to curb it has degraded the world economy and has affected almost every sector of business. As a result, various parties in diverse contracts are facing impediments in complying with their contractual obligations. In order to avoid or delay liability, the use of force majeure clauses in contracts have now become inevitable. Force majeure is defined in Black’s Law Dictionary as events ranging from acts of nature (E.g. floods and hurricanes etc.) to acts of people (E.g. riots, wars and strikes etc.) which are unforeseeable at the time the contract is closed. However, it is important for the parties to record that establishment of Covid-19 disease as a force majeure clause would differ based on the type of performance. It can be argued that an epidemic doesn’t directly give rise to a force majeure event but the events following must fulfil the elements of a force majeure clause in respective contracts. In the present scenario, it can be contended that the outbreak of Covid-19 and the worldly lockdown measures in such short span of time were completely unforeseeable and thereby no possible mitigating steps could have been taken to reduce the delay and impossibility of contractual obligations. However, determination of time extension to be granted to the defaulting party or termination of contract due to impediment would solely depend on the language of the force majeure clause in the contract pertaining to delay or prevention of performance. In the absence of a force majeure the parties can always resort to pleading impartibility, impossibility or frustration provided the subsequent impossibility is such that it destroys the very foundation of the contract thus making it impossible for performance. A mere delay in performance cannot be considered to be a valid ground for impossibility. Generally, a force majeure clause is present in contracts to prevent termination and also to absolve parties from their liabilities by delaying contractual performance during impediments, but this mechanism must not give leeway to parties for negligently avoiding performance where the effects of the unforeseen event could have been mitigated. It is evident that the outbreak of the Covid-19 disease will have long-established effects on various business sectors and related contracts that parties will get into, in the near future. Thus, parties must pay special emphasis towards including relevant force majeure clauses in their contracts in order to cover outbreak of such diseases and governmental measures as impediments. Further, parties can autonomously agree to incorporate international standards of force Majeure clauses like the ICC Force Majeure and Hardship clauses which covers epidemic under presumed impediments in both long and short form clauses. The disruptions caused due to the outbreak has resulted direct hinderances in performance of the contractual obligation by the parties and has made the scope of force majeure predominant. Thus, parties entering into contracts must take note of the same and formulate necessary changes in the formation of a contract.

*****

Footnotes

3. European Centre for Disease Prevention and Control, Disease Background of COVID-19, (2020), available at https://www.ecdc.europa.eu/en/2019-ncov-background-disease, (Last visited on May 23, 2020) ↑

4. World Health Organization, Coronavirus disease (COVID-19) pandemic, (2020), available at https://www.who.int/emergencies/diseases/novel-coronavirus-2019, (Last visited on May 23, 2020) ↑

5. UNITED NATIONS INDUSTRIAL DEVELOPMENT ORGANIZATION, Coronavirus: the economic impact, available at https://www.unido.org/stories/coronavirus-economic-impact, (Last visited on May 3, 2020) ↑

6. Bruised Indian economy to be battered further by coronavirus: Reuters poll, (March 28,2020), The Economic Times, available at https://economictimes.indiatimes.com/news/economy/indicators/bruised-indian-economy-to-be-battered-further-by-coronavirus-reuters-poll/articleshow/74858730.cms, (Last visited on May 3, 2020) ↑

7. World Trade Organization, Trade set to plunge as COVID-19 pandemic upends global economy, available at https://www.wto.org/english/news_e/pres20_e/pr855_e.htm, (Last visited on May 3, 2020) ↑

8. Annie-Lisa Dorry, The economic impact of the Coronavirus outbreak: Financial outlooks suspended, THOMSON REUTERS, (12 March, 2020), available at https://tax.thomsonreuters.com/blog/the-economic-impact-of-the-coronavirus-outbreak/, (Last visited on May 3, 2020) ↑

9. Barry Nicholas, Force Majeure and frustration, Vol. 27, No. 2/3, THE AMERICAN JOURNAL OF COMPERATIVE LAW, Pg. No. 231-245, (1979). ↑

10. Art. 7.1.7, UNIDROIT Principles of International Commercial Contracts. ↑

11. Energy Watchdog v. Central Electricity Regulatory Commission and others, (2017) 14 SCC 80. ↑

12. GV Projects & Investments (P) Ltd. v. National Highway Authority of India, (2019) 173 DRJ 717. ↑

13. China Council for the Promotion of International Trade, CCPIT Offered the First Force Majeure Certificate of Novel Coronavirus (2019-nCoV), (Feb 6, 2020), available at http://en.ccpit.org/info/info_40288117668b3d9b017019772b5706b0.html, (Last Visited on May 6,2020) ↑

14. Dr. Daniel Bachman, The economic impact of COVID-19( novel coronavirus), (March 3,2020), Deloitte ,available at https://www2.deloitte.com/us/en/insights/economy/covid-19/economic-impact-covid-19.html (Last Visited on May 7, 2020) ↑

15. Galus Australis, Global Off-Road Vehicles Market 2020 Various Manufacturing Industries: Polaris, Honda, Yamaha, Arctic Cat, Kawasaki| Impact of COVID-19, (May 12, 2020), available at https://galusaustralis.com/2020/05/635074/global-off-road-vehicles-market-2020-various-manufacturing-industries-polaris-honda-yamaha-arctic-cat-kawasaki-impact-of-covid-19/ (Last Visited on May 7, 2020 ) ↑

16. Atcor Ltd. v. Continental Energy Marketing (1996), 38 Alta. LR (3d) 229 at 243-244 (CA). ↑

17. Seadrill Ghana Operations Limited v Tullow Ghana Limited, [2018] EWHC 1640 (Comm). ↑

18. Holcim (Singapore) Pte Ltd v Precise Development Pte Ltd and another application, [2011] SGCA. ↑

19. Halliburton Offshore Services Inc. v. Vedanta Limited and Another, 2020 SCC Del 542. ↑

20. Standard Retail Pvt. Ltd. v. M/s G.S. Global Corp & Ors, Commercial Arbitration Petition (L) no. 404 of 2020. ↑

21. Lockdown weighs on economic activity: March factory output contracts a record 16.7%, The Economic Times, (May 12, 2020), (Last Visited on ), Available at https://economictimes.indiatimes.com/news/economy/indicators/industrial-production-at-record-low-shrinks-16-7-per-cent-in-march/articleshow/75696101.cms ↑

22. Sec. 2 & Sec. 2A, Epidemic Diseases Act 1897. ↑

23. Order No. 40-3/2020-DM-I-(A), Ministry of Home Affairs, Government of India, April 21,2020. ↑

24. Sec. 4(2) (C), RERA act, 2016. ↑

25. Sec. 4(1) (3), RERA act, 2016. ↑

26. Sec. 6, RERA act, 2016. ↑

27. Order no.: - 13/2020, MAHARASHTRA REAL ESTATE REGULATORY AUTHORITY, April 4, 2020. ↑

28. Rule 10(1), MAHA RERA Rules,2017. ↑

29. Rule 9 (1), Gujarat Real Estate (Regulation and Development) (General) Rules, 2017. ↑

30. Devendra Deshmukh, Harsh Parikh, Abhiraj Gandhi, COVID-19 Real Estate Impact| Not A “One Size Fits All” Scenario, Mondaq, (May 11,2020), available at https://www.mondaq.com/india/litigation-contracts-and-force-majeure/930290/covid-19-real-estate-impact-not-a-one-size-fits-all-scenario (Last Visited on May 13,2020) ↑

31. Sec. 108, Transfer of Property Act, 1882. ↑

32. Sanjay Vijaykumar, COVID-19 lockdown: Better to renegotiate business contracts, say legal experts, The Hindu, (April 6, 2020), available at https://www.thehindu.com/business/covid-19-lockdown-better-to-renegotiate-business-contracts-say-legal-experts/article31268994.eceb, (Last Visited on May 14,2020) ↑

33. No.F.18/4/2020-PPD, Ministry of Finance, Government of India, February 19,2020. ↑

34. Sec. 7.1.1., MANUAL FOR PROCUREMENT OF GOODS, 2017. ↑

35. Sumita Yadava, Primer on Indian Government’s Covid-19-Related Notifications, Mondaq, (April 25, 2020), available at https://www.mondaq.com/india/litigation-contracts-and-force-majeure/923146/primer-on-indian-government39s-covid-19-related-notifications, (Last Visited on May 15,2020) ↑

36. Sec. 56, Indian Contract Act, 1872 ↑

37. Pallavi Bedi, Classification of COVID-19 as Force Majeure event-grants relief to solar developers under the solar PPAs, The Economic Times, (April 6, 2020) ,available at https://energy.economictimes.indiatimes.com/energy-speak/classification-of-covid-19-as-force-majeure-event-grants-relief-to-solar-developers-under-the-solar-ppas/4142, (Last Visited on May 16,2020) ↑

38. No. 283/18/2020-GRID SOLAR, Ministry of New & Renewable Energy (MNRE), Government of India, March, 20, 2020. ↑

39. G Balachandar, Covid-19: Cement makers shut down factories across India, Hindu Business Line, (March 24,2020), available at https://www.thehindubusinessline.com/economy/covid-19-cement-makers-shut-down-factories-across-india/article31150233.ece, (Last Visited on May 16,2020) ↑

40. India’s unemployment rate rises to 27.11% amid COVID-19 crisis: CMIE, The Hindu, (May 5, 2020), available at https://www.thehindu.com/business/indias-unemployment-rate-rises-to-2711-amid-covid-19-crisis-cmie/article31511006.ece (Last Visited on May 16,2020) ↑

41. Sec. 25C, 25G, Industrial Disputes Act, 1947. ↑

42. Sec. 9A, Industrial Disputes Act, 1947. ↑

43. Sec. 30, Delhi Shops Act, 1954. ↑

44. Sec. 39, Karnataka Shops and Establishments Act. ↑

45. D.O. No. M-11011/08/2020-Media, Ministry of Labour &Employment, Government of India, March 20,2020. ↑

46. D.O. No: CLC (C) / Covid-19/ Instructions / LS- I, Office of the Chief Labour Commissioner (C), Ministry of Labour & Employment, March 30, 2020. ↑

47. Navneet Dubey, Force Majeure clause won’t apply to coronavirus death claims in life insurance policies, (April 7, 2020),The Economic Times (Wealth), available at https://economictimes.indiatimes.com/wealth/insure/life-insura nce/force-majeure-clause-wont-apply-to-coronavirus-death-claims-in-life-insurance-policies/articleshow/75004294.cms (Last Visited on May 17, 2020) ↑

48. All life insurance companies will process COVID-19 death claims, assures Life Insurance Council, Life Insurance Council, (April 2, 2020), available at https://www.lifeinscouncil.org/media_center/PressRelease ↑

49. G Naga Sridhar, LIC settles 16 death claims under Covid 19, (April 11,2020) , Business Line, available at https://www.thehindubusinessline.com/money-and-banking/lic-settles-16-death-claims-under-covid19/article31318703.ece (Last Visited on May 17,2020) ↑

50. PRESS RELEASE, ADDITIONAL GRACE PERIOD OFR LIFE INSURANCE POLICIES, Insurance Regulatory and Development Authority of India, May 9, 2020, available at https://www.irdai.gov.in/ADMINCMS/cms/Uploadedfiles/Press%20Release%200905%20.pdf ↑

51. Sec. 216, Restatement (Second) Of Contracts. ↑

52. Lakeman v. Pollard, 43 Me. 463 (1857). ↑

53. KSRTC v. Mahadeva Shetty, (2003) 7 SCC 197. ↑

54. Li Ching Wing v. Xuan Yi Xiong, [2004] 1 HKLRD 754. ↑

55. Sec. 56, Indian Contract Act,1872. ↑

56. Satyabrata Ghose vs. Mugneeram Bangur and Others, AIR 1954 SC 44. ↑

How to cite

Deborshi Sarkar & Ridhima Mehrotra, Analysing the Scope of Force Majeure in the Light of Covid-19., 3 Int'l J.L. Mgmt. & Human. 1695 (2020).

Cite this article

Deborshi Sarkar & Ridhima Mehrotra, Analysing the Scope of Force Majeure in the Light of Covid-19., 3 Int'l J.L. Mgmt. & Human. 1695 (2020).
Chat with us